Industrial repair
Click on the image to enlarge.
Abalon has worked in petrochemical plants, gas plants, rail yards, airports, dams, water treatment plants, etc. Our staff has safety training that includes Safe Trenching courses, First aid, WHMIS and is now enrolled in the Alberta WCB COR Program.
Step 1
We set up a trailer, bin and toilet. All are required for longer projects.
Step 2
In this project, the trees needed to be removed.
Step 3
Trains were running the entire duration of the project.
Step 4
High voltage, communications, gas, water and sewer lines were all encountered.
Step 5
Trees were recycled.
Step 6
Even the boss gets in on the action.
Step 7
The berm needed removal to allow for foundation repair.
Step 8
Soil was stored on site.
Step 9
Documentation is a must on larger projects. Pictures and a log are kept for the duration.
Step 10
Concrete in the way is saw cut, broken and recycled.
Step 11
Hand excavation is required to expose all utilities.
Step 12
Supervisor gives pointers to concrete breaker.
Step 13
Soil was moved away from the excavation.
Step 14
Entrances were maintained and operable at all times.
Step 15
Safety is of utmost importance at Abalon.
Step 16
Our operators have a golden touch.
Step 17
Supervisor guides shoring box.
Step 18
Shoring boxes are a must; this project was 12 feet deep.
Step 20
Perforated drain pipe failed. It was plugged and full of roots which caused basement to leak.
Step 21
Services cause headaches for shoring process.
Step 22
Walls were cleaned, cracks were chipped and caulked with polyurethane.
Step 23
The magnitude of this repair is evident in this picture.
Step 24
Safe worker is a happy worker.
Step 25
Safety gear used as waterproofing membrane is troweled on.
Step 26
Waterproofing is allowed to dry.
Step 27
Foundation wrap was installed along with a 6 inch weeping tile and washed rock.
Step 28
Project is backfilled in lifts and tamped.
Step 29
Excavations can be sloped back 45% or shored depending on the soil conditions.
Step 30
Shores must be moved many times to allow for cleaning, chipping, patching, waterproofing and wrapping.
Step 31
Flashing is used to protect the foundation wrap at the top.
Step 32
The work is endless and needs to be done safely and correctly.
Step 33
Portion of concrete entrance that was re-poured after repairs.
Step 34
Backfilling by hand and with machines.
Step 35
The berm is reinstalled.
Step 36
Berm is hydro seeded for grass to grow back.
Call us for an estimate today!
403.230.3050 - Calgary
1.877.441.3050
Toll free outside Calgary
Prev
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
Next