Abalon logo Request an estimate
 

Industrial repair

Click on the image to enlarge.
Click to enlarge

Abalon has worked in petrochemical plants, gas plants, rail yards, airports, dams, water treatment plants, etc. Our staff has safety training that includes Safe Trenching courses, First aid, WHMIS and is now enrolled in the Alberta WCB COR Program.

Click to enlarge

Step 1

We set up a trailer, bin and toilet. All are required for longer projects.

Click to enlarge

Step 2

In this project, the trees needed to be removed.

Click to enlarge

Step 3

Trains were running the entire duration of the project.

Click to enlarge

Step 4

High voltage, communications, gas, water and sewer lines were all encountered.

Click to enlarge

Step 5

Trees were recycled.

Click to enlarge

Step 6

Even the boss gets in on the action.

Click to enlarge

Step 7

The berm needed removal to allow for foundation repair.

Click to enlarge

Step 8

Soil was stored on site.

Click to enlarge

Step 9

Documentation is a must on larger projects. Pictures and a log are kept for the duration.

Click to enlarge

Step 10

Concrete in the way is saw cut, broken and recycled.

Click to enlarge

Step 11

Hand excavation is required to expose all utilities.

Click to enlarge

Step 12

Supervisor gives pointers to concrete breaker.

Click to enlarge

Step 13

Soil was moved away from the excavation.

Click to enlarge

Step 14

Entrances were maintained and operable at all times.

Click to enlarge

Step 15

Safety is of utmost importance at Abalon.

Click to enlarge

Step 16

Our operators have a golden touch.

Click to enlarge

Step 17

Supervisor guides shoring box.

Click to enlarge

Step 18

Shoring boxes are a must; this project was 12 feet deep.

Click to enlarge

Step 19

More shoring.

Click to enlarge

Step 20

Perforated drain pipe failed. It was plugged and full of roots which caused basement to leak.

Click to enlarge

Step 21

Services cause headaches for shoring process.

Click to enlarge

Step 22

Walls were cleaned, cracks were chipped and caulked with polyurethane.

Click to enlarge

Step 23

The magnitude of this repair is evident in this picture.

Click to enlarge

Step 24

Safe worker is a happy worker.

Click to enlarge

Step 25

Safety gear used as waterproofing membrane is troweled on.

Click to enlarge

Step 26

Waterproofing is allowed to dry.

Click to enlarge

Step 27

Foundation wrap was installed along with a 6 inch weeping tile and washed rock.

Click to enlarge

Step 28

Project is backfilled in lifts and tamped.

Click to enlarge

Step 29

Excavations can be sloped back 45% or shored depending on the soil conditions.

Click to enlarge

Step 30

Shores must be moved many times to allow for cleaning, chipping, patching, waterproofing and wrapping.

Click to enlarge

Step 31

Flashing is used to protect the foundation wrap at the top.

Click to enlarge

Step 32

The work is endless and needs to be done safely and correctly.

Click to enlarge

Step 33

Portion of concrete entrance that was re-poured after repairs.

Click to enlarge

Step 34

Backfilling by hand and with machines.

Click to enlarge

Step 35

The berm is reinstalled.

Click to enlarge

Step 36

Berm is hydro seeded for grass to grow back.

Call us for an estimate today!

403.230.3050 - Calgary

1.877.441.3050
Toll free outside Calgary

Prev 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Next